The paper describes the measuring systems and methodology for acquiring traction power measurements on the on-board traction systems of two metro trains and three 750 V DC rectifier substations in the A. .
••Methodology described for traction power measurements on train. .
Harnessing the wasted train braking energy of Metro trains and utilizing it either in complementing the power supply of trains or using it in other electrical consumptions in Metro stations. .
The steps taken in setting up, organizing and executing the electrical measurements on-board the 2 trains and on 3 rectifier substations were the following:•a). .
Once the measuring equipment was installed on-board the 2 trains and in the 3 Rectifier Substations, the following steps were taken:•a). .
Measurements were conducted in the three consecutive traction substations at Sepolia station, Ag. Antonios station and Peristeri station on Metro Line 2. The required engineering for e. [pdf]